 Update 4/22/16

Construction Activity on the Courthouse Expansion Project Picks Up – Walkway to Close with Tunnel Opening

Starting next week, the walkway connecting the Main Courthouse and Babcox Justice Center  will be closed to allow for major work on the bridge.

The section of the bridge directly south of Washington Street will begin to be demolished on or around May 2. The other portion (over Washington Street) will undergo a makeover that includes removing the roofing, brick and windows, and transforming the appearance of the bridge’s interior.  The bridge will be closed for approximately two years.

This bridge closing means employees and the public will have to walk outside along Washington Street, or County Street, from the main entrance to Babcox (Courtrooms C120 (Bond Court), C150, C220 and C221). This is .19 miles or 1000 feet, about a three minute walk. There will be a pathway outside the south entrance of the courthouse connecting to County Street until Washington Street is opened this summer.


Update 9/21/15

Construction on the Lake County Courthouse is progressing and requires the full closure of County St.   Fencing and concrete barriers will be installed on County St for closures and traffic restrictions.  Below is  a summary of the impacts and the approved detour plan that will be implemented during construction.

Washington St.

  • Washington St will remain fully closed from MLK Ave. to County St.  Reference detour plan below for alternate route.
  • The Washington Street Court Entrance will remain open, however, pedestrian traffic from County Street will no longer have direct access to this entrance. Access to the Courts complex can be gained at the North Entrance and/or the Babcox Courts Entrance.

S. County St.

  • S. County St, will be fully closed from Washington St. to Water St.  Reference detour plan below for alternate route.

County St. Detour


Update 4/16/15

Construction on the Lake County Courthouse is expected to begin on or about May 1, 2015.  Fencing and concrete barriers will be installed on Washington St and County St for closures and traffic restrictions.  Below is  a summary of the impacts and the approved detour plan that will be implemented during construction.  This phase is expected to last approximately 12 months.

Washington St.

  • Washington St will be fully closed from MLK Ave. to County St.  Reference detour plan below for alternate route.
  • The Washington Street Court Entrance will remain open, however, pedestrian traffic from County Street will no longer have direct access to this entrance. Access to the Courts complex can be gained at the North Entrance and/or the Babcox Courts Entrance.

S. County St.

  • All on-street metered parking between Water St. and Washington St. will be unavailable.   Parking in these locations is prohibited.
  • Vehicular traffic will be shifted to the east side of County St.
  • Pedestrian traffic will be shifted to the east side of County St.

LCCE Tunnel Traffic for Website


Update 4/9/15

Construction will begin Monday, April 13 on new underground utilities necessary for the Lake County Courthouse Expansion.

This work will impact the following streets:

S. County St.

  • Parking will be prohibited between Water St. and Washington St.  Signage will be post with dates.
  • Road will be closed to northbound traffic.  Traffic will be detoured around work zone via Water St., Genessee St., and Washington St.
    Be aware of posted signage and new traffic patterns

Informational Meeting Dec. 9

Please join Lake County and Clark Construction for an informational meeting on the construction of the Lake County Courthouse Expansion Project. Representatives from the County and Clark will discuss and review the construction schedule, construction plans, and the impact of this project on the downtown area.

Date & Time: 4 p.m. to 5 p.m. – Tuesday, December 9, 2014
Location: Lake County Sheriff’s Office, Training Room
25 S Martin Luther King Jr Avenue, Waukegan
Please RSVP by sending an email to
info@lakecountycourthouseexpansion.com.


Update 9/26/14

Construction will begin Monday, September 29 on new underground electrical utilities necessary for the Lake County Courthouse Expansion.

This work will impact the following streets:

S. Martin Luther King Jr. Ave.

  • Parking will be prohibited between Water St. and Washington St.  Signage will be post with dates.
  • Two way traffic will be shifted around work zones, be aware of new traffic patterns.

S. County St.

  • Parking will be prohibited between Water St. and Washington St.  Signage will be post with dates.
  • Road will be closed to northbound traffic.  Traffic will be detoured around work zone via Water St., Genessee St., and Washington St.  Be aware of posted signage and new traffic patterns